CIO Influence
CIO Influence News Datacentre

Microsoft Restarts 810 MW North Carolina Data Center Build After Seven-Month Pause

Microsoft Restarts 810 MW North Carolina Data Center Build After Seven-Month Pause

Aterio Logo

After ~7 months of inactivity, Aterio’s satellite monitoring detects simultaneous re-mobilization at Microsoft’s three campuses in Catawba County, NC.

Aterio, a Data-as-a-Service provider tracking U.S. infrastructure development, has identified renewed construction activity at all three of Microsoft’s permitted data center campuses in Catawba County, North Carolina. Satellite monitoring conducted in January and February 2026 captured simultaneous re-mobilization signals at the Lyle Creek, Boyd Farm, and Stover North campuses — sites that had shown little to no activity since approximately Q2 2025.

The pattern is hard to ignore, three dormant campuses, all moving at once. That’s the kind of early signal we look for in every project.”

— Sergio Toro, CEO, Aterio

The development marks a notable reversal. In April 2025, Microsoft signaled it was slowing or pausing certain data center builds, and Aterio’s ongoing satellite tracking of the North Carolina campuses confirmed limited progress in the months that followed. The new activity — detected concurrently across all three sites — suggests a coordinated restart rather than isolated incremental work.

Scale of the Build
Based on U.S. Army Corps of Engineers public notices filed for each campus, each site is planned for five 48 MW data center buildings supported by dedicated Duke Energy substation infrastructure. Lyle Creek is served by two substations; Boyd Farm and Stover North each by one.

Also Read: CIO Influence Interview With Jake Mosey, Chief Product Officer at Recast

Aterio’s analysis of comparable Microsoft hyperscale deployments — including buildings using the same approximately 250,000 sq ft “Ballard” design configuration — indicates each building is typically supported by approximately 20 backup generators, implying roughly 54 MW of total nameplate capacity per building when accounting for redundancy, cooling, and electrical overhead.

This produces the following capacity range for the three-campus program:
– Low case (Critical IT, filing-supported): ~720 MW (15 buildings × 48 MW)
– High case (generator-backed nameplate): ~810 MW (15 buildings × ~54 MW)

Site-Level Observations
At Lyle Creek, Aterio’s satellite analysis detected renewed movement on concrete slabs following approximately seven months of inactivity. At Boyd Farm, analysts observed substation-level progress alongside active land grading in the southern portion of the campus. At Stover North, significant substation advancement was noted alongside more limited activity on the concrete building pads.

Activation Timeline
Even under an aggressive construction ramp, Aterio estimates first building activations are unlikely before Q3 2027, with a more realistic expectation of late Q4 2027 to Q1 2028 for initial online capacity, followed by a phased rollout across the remaining 12 buildings. Local economic development disclosures position Microsoft’s investment as a phased, multi-year program with a minimum $1 billion commitment over 10 years, with the project structured to allow completion through 2032.

Catch more CIO Insights: Why CIOs are becoming chief risk orchestrators?

[To share your insights with us, please write to psen@itechseries.com ]

Related posts

Cynet Security Announces Jason Magee as Chief Executive Officer

Business Wire

Auth0 Releases State Of Secure Identity Report, Highlighting The Most Pervasive Threats To Digital Identities

CIO Influence News Desk

immudb First Immutable Open Source Database to be FedRAMP Compliant

CIO Influence News Desk